Loading...
Data Center Frontier: Ohio sets new precedent, AEP's power rules shift data center cost burden
Published by datacenterfrontier.com·Recorded Nov 4, 2026
Open the originalSupports: Special tariffs can make data centers pay for the grid built for them. Under AEP Ohio's tariff, approved in July 2025, new data centers of 25 MW or more pay for at least 85% of their contracted power for up to 12 years, whether they use it or not.